Application of Technology Improvement of Construction Scheme  in Deep Hole Blasting of a Gold Mine

LI Qiyue,WEI Jiarui,LI Yi,HUANG Wulin,ZHANG Chengjun   

  1. School of Resources and Safety Engineering,Central South University,Changsha   410083,Hunan,China
  • Received:2015-06-08 Revised:2015-07-25 Online:2016-06-28 Published:2016-10-08

Abstract:

Deep-hole blasting is an effective way to cut the raise of the deep hole,but the borehole deviation has become an important factor to restrict the success of deep hole blasting.Based on the analysis of the borehole deviation and the existing problems in the scene in the 680 section of a gold mine in Shandong Province,the construction scheme is improved on the basis of the original design.Firstly,the three parameters,such as the compensation coefficient,the breaking angle and the free surface coefficient,are put forward to determine the location of patching holes and initiation sequence.Secondly,the methods of charging with different explosion brisance explosives and multiple blasts are used.Volume of emulsion explosives are used at the first detonation by manual charging,which have high explosive compression but low charging efficiency.The second detonation uses special modified granular anfo explosives by mechanical charging,greatly improves the efficiency of charging,and releases less poisonous gas. Finally,the three problems of serious borehole deviation,charging difficulties and insufficient segments of detonators were solved in the cutting raise blasting.The blasting test results are analyzed,which proves that the construction scheme is proved to be feasible,and it has certain guiding value for similar projects.

Key words: deep hole blasting, cut raise, cut blasting, borehole deviation, construction scheme

CLC Number: 

  • TD323

[1] 张奇,杨永琦,员永峰,等.直眼掏槽爆破效果的影响因素分析[J].岩土力学,2001,22(2):144-150.
[2] 刘优平,龚敏,黄刚海.深孔爆破装药结构优选数值分析方法及其应用[J].岩土力学,2012,33(6):1883-1888.
[3] 陈士海,魏海霞,薛爱芝.坚硬岩石巷道中深孔掏槽爆破试验研究[J].岩石力学与工程学报,2007,26(增):3498-3502.
[4] 李启月,李夕兵,范作鹏,等.深孔爆破一次成井技术与应用实例分析[J].岩石力学与工程学报,2013,32(4):664-670.
[5] 于清军,于清源,路仁江,等.浅孔留矿与中深孔爆破联合回采复杂矿体技术研究[J].黄金科学技术,2011,19(1):49-50.
[6] 吕志云,曾云煜.无切井扇形中深孔爆破拉槽法在红旗沟—深水潭金矿的应用[J].黄金科学技术,2015,23(4):72-74.
[7] 周传波,谷任国,罗学东.坚硬岩石一次爆破成井掏槽方式的数值模拟研究[J].岩石力学与工程学报,2005,24 (13):2298-2302.
[8] 赵国彦,赵井清,李启月.9孔桶形掏槽一次成井技术[J].科技导报,2013,31(16):21-25.
[9] Sterk P V.Development of drop raise blasting at Homestake mine[C]//Proceedings of the 17th Annual Conference onExplosives and Blasting Technique[Sl]:[s.n.],1991:239-250.
[10] 李夕兵.凿岩爆破工程[M].长沙:中南大学出版社,2011:184-246.
[11] 杨荣彦,穆永庆,刘广兴.洛钼集团矿山公司深孔爆破一次成井的试验研究[J].采矿技术,2012,12(6):68-72.
[12] Langerfor S U,Kihlstorm B.The modern technique of rock blasting[M].New York:John Willey & Sobs Company,1963:25-32.
[13] 罗勇,沈兆武.炮孔合理堵塞长度的研究[J].岩土工程技术,2006,20(1):25-28.
[14] 李廷春,刘洪强.一次成井掏槽爆破炮孔合理封堵长度研究[J].中国矿业大学学报,2012,41(3):384-389.
[15] 郝亚飞,李海波,刘恺德,等.单自由面爆破振动特征的炮孔堵塞长度效应[J].岩土力学,2011,32(10):3105-3110.
[16] 李启月,刘冰川,陈亮,等.深孔爆破一次成井炮孔合理堵塞长度[J].科技导报,2013,31(19):9-15.
[17] 李新平,朱瑞赓,夏元友.中深孔双螺旋掏槽爆破的破碎机理与设计应用[J].岩土工程学报,1997,19(2):84-88.
[18] 亨利奇.爆炸动力学及其应用[M].熊建国,译.北京:科学出版社,1987:305-306.
[19] 杨国梁,姜琳琳,杨仁树.复式楔形深孔掏槽爆破研究[J].中国矿业大学学报,2013,42(5):754-760.
[20] 林大能,陈寿如.空孔直眼掏槽成腔模型理论与实践分析[J].岩土力学,2005,26(3):479-484.
[21] Henrych J.The Dynamics of Explosion and Its Use[M].New York:Elesvier Scientific Publishing Company,1979.
[22] 哈努卡耶夫.矿岩爆破物理过程[M].刘殿中,译.北京:冶金工业出版社,1980.
[23] 王伟,李小春,石露,等.深层岩体松动爆破中不耦合装药效应的探讨[J].岩土力学,2008,29(10):2837-2842.
[24] 卢文波,Hustrulid W.质点峰值振动速度衰减公式的改进[J].工程爆破,2002,8(3):1-4.

[1] CAO Shirong,XIAO Weijing,LI Yongxin,WANG Xiaojun,ZHUO Yulong,FENG Xiao . Study on AE Characteristics of Cyclic Loading and Unloading of Ballast Cemented Backfilling Body [J]. Gold Science and Technology, 2017, 25(3): 92-97.
[2] SUN Yang,LUO Liming,DENG Hongwei. Stability Analysis and Parameter Optimization of Stope in Deep Metal Mines [J]. Gold Science and Technology, 2017, 25(1): 99-105.
[3] SHI Xiuzhi,FAN Yuqian,SHANG Xueyi. Strength Prediction of Filling Body Based on PCA and BP Neural Networks [J]. Gold Science and Technology, 2016, 24(3): 64-69.
[4] ZHUO Yulong,CHEN Chen,CAO Shirong,WANG Xiaojun,FENG Xiao. Effects of Ballast on Strength Characteristics and Damage Evolution of Filling Body [J]. Gold Science and Technology, 2016, 24(3): 76-80.
[5] DAI Xingguo,TANG Ling,CHEN Zengjian,NIE Zheng. Dynamic Optimization of Stoping Scheme Based on λ Fuzzy Measure and Choquet Integral [J]. Gold Science and Technology, 2016, 24(2): 1-7.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!