Study on the Method of Backward Vertical Striping Sublevel Filling Mining without Sill Pillar

MA Yunqing,WANG Ruixing,HE Shunbin,WANG Hui,YU Changxian,QIU Yunsheng   

  1. Sanshandao Gold Mine,Shandong Gold Mining (Laizhou) Co.,Ltd.,Laizhou   261442,Shandong,China
  • Received:2014-05-20 Revised:2014-06-15 Online:2014-08-28 Published:2014-12-24

Abstract:

Combined with the application situation of current mining method in Sanshandao gold deposit,this paper has carried a brief description on the scheme proposed,the theoretical basis and the research purpose for the method of backward vertical striping sublevel filling mining without sill pillar,and also has focused on the introduction of mining engineering arrangement,stope production organization form,stope construction technology and so on.By comparatively studied and summarized the mining method indicators in the existing panels in mine area,some advantages have been derived for this method,such as the sublevel stoping dramatically reducing the quasi project cost,the medium-length hole ore blast reducing the cost of drilling and blasting,the tilt striping stoping realized the fixed-point out of mine,which not only improved the efficiency of the out of mine,but also avoided the filling body collapse caused by secondary dilution.The vertical slitting stoping,effectively controlled the caving of stope roof and upper plate.The back stoping and the two wings return air,improved stope safety and ventilation,etc.With the application of a number of innovative technologies,for example patio construction and to cut the generation of digging,the problem of the patio up-dig of medium-length hole was solved which troubled the mine many years.In short,the method is reasonable designed and its construction technology is easy to grasp.It has a great value in popularization and application.

Key words: vertical striping, sublevel filling, medium-length hole, backward, sublevel stoping

CLC Number: 

  • TD85

[1] 解世俊.金属矿床地下开采[M].北京:冶金工业出版社,1986.
[2] 黄胜生.国内外缓倾斜中厚矿体采矿方法现状[J].矿业研究与开发,2001,21(4):21-24.
[3] 钟义旒.金属矿床开采[M].北京:冶金工业出版社,1998.
[4] 况世华,何丽华.缓倾斜极薄矿脉开采新方法研究[J].云南冶金,2009,38(1):10-14.
[5] 韦章能.安庆铜矿缓倾斜薄矿体采矿工艺研究[J].有色金属(矿山部分),2006,58(3):10-11.
[6] 古德生,李夕兵.现代金属矿床开采科学技术[M].北京:冶金工业出版社,2006:10-35.
[7] 于润沧.采矿工程师手册(下)[M].北京:冶金工业出版社,2009:21-30.
[8] 《采矿设计手册》编委会.《采矿设计手册》[M].北京:中国建筑工程出版社,1987.

[1] YANG Mingcai, SHENG Jianlong, YE Zuyang, DONG Shu. Analysis of Sensitivity Factors of Open-pit Mine Slope Stability and Impact Based on FlAC3D [J]. Gold Science and Technology, 2018, 26(2): 179-186.
[2] SHI Caixing, GUO Lijie, LI Wenchen, ZHANG Dan. Study on Filling Cementitious Materials Based on Lead-Zinc Smelting Slag and Its Application [J]. Gold Science and Technology, 2018, 26(2): 160-169.
[3] LIU Dingyi, WANG Liguan, CHEN Xin, ZHONG Deyun, XU Zhiqiang. Study on Multi Objective Optimization and Application of Medium and Long Term Plan for Underground Mine [J]. Gold Science and Technology, 2018, 26(2): 228-233.
[4] LIN Ge, GONG Fengqiang. Research on Evaluation Index of Red Sandstone Instability Under Different Stress [J]. Gold Science and Technology, 2018, 26(2): 195-202.
[5] CAO Shirong,HAN Jianwen,LI Yongxin,WANG Xiaojun,FENG Xiao,ZHUO Yulong. Damage Analysis of Solid Waste Rock Cemented Filling Body Based on Acoustic Emission Probability Density Function [J]. Gold Science and Technology, 2017, 25(6): 92-98.
[6] DENG Gao,YANG Shan. Analysis of Mineral Resources Utilization Based on Grey Cluster and Grey Prediction Combined Model [J]. Gold Science and Technology, 2017, 25(5): 85-92.
[7] DING Jianfeng. Research on the Ore Bunker Treatment of a Gold Mine [J]. Gold Science and Technology, 2017, 25(4): 52-57.
[8] LI Zongnan,GUO Lijie,YU Bin,SHI Caixing. Shearing Thinning Behavior of High Concentration Slurry Based on Bingham Model [J]. Gold Science and Technology, 2017, 25(4): 33-38.
[9] BAI Zhaoyang,WANG Guowei,ZHANG Peng,LIU Shuanping. Research on Pillaring Blasting Location Under Level Gob Group Conditions [J]. Gold Science and Technology, 2017, 25(4): 81-86.
[10] WANG Xinmin,RONG Shuai,ZHAO Maoyang,ZHANG Qinli . Concentration Equipment Optimization Based on Variable Weight Theory and TOPSIS [J]. Gold Science and Technology, 2017, 25(3): 77-83.
[11] XU Huaihao,LI Jinyou. Application Practice of Increasing Production and Reducing Consumption in Grinding System of Dayingezhuang Gold Mine [J]. Gold Science and Technology, 2017, 25(3): 116-120.
[12] HU Jianhua,YANG Chun,ZHOU Bingren,ZHOU Keping,ZHANG Shaoguo. Simulation of Fracture Propagation and Optimization of Parameters for Smooth Blasting of Coping in Roadway [J]. Gold Science and Technology, 2017, 25(2): 45-53.
[13] DENG Hongwei,YANG Yiquan,DENG Junren,LIU Chuanju,ZHOU Yanlong. Study on Mining Sequence of Deep Orebody Under High Stress Environment Below Goaf [J]. Gold Science and Technology, 2017, 25(2): 62-69.
[14] JIA Mintao,WANG Qunfang,WU Lengjun. Research Status and Prospect of Thermal Environmental Control Technology Under Deep Mining [J]. Gold Science and Technology, 2017, 25(2): 83-88.
[15] LIU Liansheng,LAN Depei,ZHANG Shenghui,PAN Rongsen,CAI Jiande. Research on Application of Frequency Division Multiple Access Misfire Detection Technology and System in Deep Hole Blasting [J]. Gold Science and Technology, 2017, 25(2): 54-61.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!