Gold Science and Technology ›› 2013, Vol. 21 ›› Issue (6): 63-67.

Previous Articles     Next Articles

Stability Evaluation for Mine Gob Areas Based on AHP and Fuzzy Synthetic Judgement Theory

HAO Xubin, YANG Lihui, WAN Sheng   

  1. Jiaojia Gold Mine,Shandong Gold Mining (Laizhou) Co.,Ltd,Laizhou   261441,Shandong,China
  • Received:2013-06-06 Revised:2013-08-19 Online:2013-12-28 Published:2014-05-09

Abstract:

Based on the engineering background of Shi rengou iron mine, according  to the practical  condition,using multi-stage fuzzy synthetic judgement theory,this paper makes a two-stage fuzzy synthetic judgement model of the stability of mine gob area with 15 factors.The fuzzy evaluation matrix is made using expert evaluation method and three-phase linear membership function method to evaluate the qualitative and quantitative factors.The weight of factors are determined using AHP,then a weight matrix is made.The concourse are then calculated together with the evaluating matrix to complete the synthetic evaluation of gob area stability variable.The results show that the evaluation results can accurately reflect the stability of mine gob area.This is a effective method to analyze the stability of mine gob area.

Key words: AHP, fuzzy synthetic judgement, stability evaluation, goaf

CLC Number: 

  • TD853

[1] 吴丽萍,吴世跃,郭勇义.模糊数学在矿山安全综合评价中的应用[J].太原理工大学学报,2006,37(2):131-133,138.
[2] 杨扬,冯乃琦,余珍友,等. 基于层次分析和模糊数学的采空区稳定性综合评价[J].有色金属(矿山部分),2008,60(5):37-39,42.
[3] 李新春,张幼蒂. 露天采矿工艺选择的神经网络模糊决策系统研究[J].黄金科学技术,1999,7(增):39-41.
[4] 朱川曲.回采巷道围岩稳定性分类及松动圈尺寸预测[J]. 黄金科学技术,1999,7(增):63-66.
[5] 冯保成.模糊数学实用集萃[M].北京:中国建筑工业出版社,1991.
[6] 曹庆林,桑玉发.应用人工神经网络方法划分采场顶板安全等级[J].矿冶工程,1995,15(3):8-11.
[7] 马云龙,刘铁雄,陈科平,等.高峰105号矿体采空区稳定性模糊综合评价[J].西部探矿工程,2010,(6):1-3.
[8] 张晓君.影响采空区稳定性的因素敏感性分析[J].矿业研究与开发, 2006,26(1):14-16.
[9] 《工程地质手册》编写委员会.工程地质手册[M].(第4版).北京:中国建筑工业出版社,2007.
[10] 曹文贵, 张永杰.地下结构岩体质量分类的变权重二级模糊综合评判方法研究[J].岩石力学与工程学报,2006,25(8):1612-1618.
[11] 王新民,赵彬,张钦礼.基于层次分析和模糊数学的采矿方法选择[J].中南大学学报:自然科学版,2008,39(5):875-880.
[12] 杨纶标,高英仪.模糊数学原理及应用[M].(第4版).广州:华南理工大学出版社,2006.
[13] 温庆华, 童保国. 哈拉沟煤矿煤巷顶板稳定性影响因素分析[J].煤炭技术,2009,28(1):96-98.
[14] 张林, 杨志刚, 钱庆强, 等. 溶洞顶板稳定性影响因素正交有限元法分析[J].中国岩溶, 2005,24(2):156-159.
[15] 吴启红,彭振斌,陈科平,等.矿山采空区稳定性二级模糊综合评判[J].中南大学学报:自然科学版,2010,41(2):661-667.

[1] SHI Caixing, GUO Lijie, LI Wenchen, ZHANG Dan. Study on Filling Cementitious Materials Based on Lead-Zinc Smelting Slag and Its Application [J]. Gold Science and Technology, 2018, 26(2): 160-169.
[2] LIU Dingyi, WANG Liguan, CHEN Xin, ZHONG Deyun, XU Zhiqiang. Study on Multi Objective Optimization and Application of Medium and Long Term Plan for Underground Mine [J]. Gold Science and Technology, 2018, 26(2): 228-233.
[3] LIN Ge, GONG Fengqiang. Research on Evaluation Index of Red Sandstone Instability Under Different Stress [J]. Gold Science and Technology, 2018, 26(2): 195-202.
[4] CAO Shirong,HAN Jianwen,LI Yongxin,WANG Xiaojun,FENG Xiao,ZHUO Yulong. Damage Analysis of Solid Waste Rock Cemented Filling Body Based on Acoustic Emission Probability Density Function [J]. Gold Science and Technology, 2017, 25(6): 92-98.
[5] DING Jianfeng. Research on the Ore Bunker Treatment of a Gold Mine [J]. Gold Science and Technology, 2017, 25(4): 52-57.
[6] LI Zongnan,GUO Lijie,YU Bin,SHI Caixing. Shearing Thinning Behavior of High Concentration Slurry Based on Bingham Model [J]. Gold Science and Technology, 2017, 25(4): 33-38.
[7] BAI Zhaoyang,WANG Guowei,ZHANG Peng,LIU Shuanping. Research on Pillaring Blasting Location Under Level Gob Group Conditions [J]. Gold Science and Technology, 2017, 25(4): 81-86.
[8] XU Huaihao,LI Jinyou. Application Practice of Increasing Production and Reducing Consumption in Grinding System of Dayingezhuang Gold Mine [J]. Gold Science and Technology, 2017, 25(3): 116-120.
[9] WANG Xinmin,RONG Shuai,ZHAO Maoyang,ZHANG Qinli . Concentration Equipment Optimization Based on Variable Weight Theory and TOPSIS [J]. Gold Science and Technology, 2017, 25(3): 77-83.
[10] LIU Zhixiang,GONG Yongchao,LI Xibing. Study on the Backfilling Material Properties Based on Fractal Theory and BP Neural Network [J]. Gold Science and Technology, 2017, 25(2): 38-44.
[11] HU Jianhua,YANG Chun,ZHOU Bingren,ZHOU Keping,ZHANG Shaoguo. Simulation of Fracture Propagation and Optimization of Parameters for Smooth Blasting of Coping in Roadway [J]. Gold Science and Technology, 2017, 25(2): 45-53.
[12] JIA Mintao,WANG Qunfang,WU Lengjun. Research Status and Prospect of Thermal Environmental Control Technology Under Deep Mining [J]. Gold Science and Technology, 2017, 25(2): 83-88.
[13] XIAO Weijing,CHEN Chen,LI Yongxin,WANG Xiaojun,CAO Shirong,HAN Jianwen. Creep Experiment and Model of Deep Limestone Under Step Loading [J]. Gold Science and Technology, 2017, 25(2): 76-82.
[14] CAO Shirong,HAN Jianwen,XIAO Weijing,ZHUO Yulong,WANG Xiaojun,FENG Xiao. Study on Stress-Strain Relationship of Cemented Backfilling with Different Aggregate Content [J]. Gold Science and Technology, 2017, 25(1): 93-98.
[15] ZHAO Guoyan,HOU Jun,ZHANG Xiaorui,LI Diyuan,WANG Tao. Study on the Mechanical Properties of the Phosphogypsum Paste Filling Material [J]. Gold Science and Technology, 2016, 24(5): 7-12.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!