Application of Long-hole Shock Controlled Blasting in Sanshandao Gold Mine

YU Changxian,ZHAO Mingxuan,LI Xiaodong   

  1. Sanshandao Gold Mine,Shandong Gold Mining (Laizhou) Co.,Ltd.,Laizhou   261442,Shandong,China
  • Received:2012-05-01 Revised:2012-06-20 Online:2012-08-28 Published:2013-01-23

Abstract:

In order to reduce the loss of safety pillar,using pit excavation method to recovery the orebody from surface 10 m to -2.0 m within the immediate mining area of the Sanshandao gold mine.Because subject to site layout of the plant and taking account of speeding up the construction schedule and reducing the production cost,we choose the blast pattern of long-hole shock controlled blasting.To maximize the reduction of blasting vibration on the surrounding environment,proposed the program of pre-splitting blasting on pit outline first,main blast of longhole shock controlled blasting in deep hole later.In this paper,parameters of two controlled blasting method is determined in detail,blasting effect is analyzed.Elaborate on blasting program choosing,blasting parameter optimization,initiation network design and security checking and protection,provides a reference for similar projects.

Key words: Pit excavation, Pre-splitting blasting, Long-hole shock controlled blasting, Millisecond blasting, Blasting network

CLC Number: 

  • TD235

[1] 于亚伦.工程爆破理论与技术[M].北京:冶金工业出版社,2004.
[2] 汪旭光.爆破手册[M].北京:冶金工业出版社,2010.
[3] GB6722-2003.爆破安全规程[S].北京:中国安全爆破协会,2004.
[4] 林学圣.土石爆破[M].南京:解放军理工大学工程兵学院出版社,1985.
[5] 崔正荣,梁开水,赵明生,等.中深孔爆破在金山采场的应用[J].爆破,2007,24(2):39-41.
[6] 陶颂霖.凿岩爆破[M].北京:冶金工业出版社,1997.