Discussion on the Relationship between the Geo-stress and Gateway Stability of Nalin Gold Mine

NIE Shenglu1,CAO Hongzheng2   

  1. 1.Zhongyi Industry and Trade Co.,Ltd,Beijing 100020,China;
    2.Laozuoshan Gold Mine,Qitaihe 154625,Heilongjiang,China
  • Received:2010-08-02 Revised:2010-11-24 Online:2010-12-30 Published:2011-03-10

Abstract:

We describe the method to explore the Carlin-type deposits with low grade,tilt,and middle thick orebody located in Nalin gold mine.It is proved that sublevel caving mining method can only be applied in this mine.Different problems have been encountered in testing and production such as stability of rock,possible deformation of the tunnel in the orebody during excavation soon after the tunnel is completed.Its stability can not last more than 3 ~ 4 month even with puffanchor.Large-scale falling may happen when gob doesn’t exist longer enough or exposure space is not large enough although depth of exploitation is less than 150 m due to the introduction of adit development. But it is sufficient to prove greater mine residual stress from geological structure causes poor stability of tunnel during the formation of deposits.It is advised that tunnel be excavated at the foot of the edge of the orebody and to improve stability by technogy of hole to hole blowing method.We analyze and discuss the above-mentioned issues in order to grasp the nature of residual stress and stability of tunnel which will serve mine production, change from passive to active,nature to freedom to achieve safe,efficient and economical development of mineral resources purposes.

Key words: Sublevel Caving Method, Residual stress, Tunnel stability, Covered rock, Analysis and discussion

CLC Number: 

  • TD353

[1]刘健,樊满华,邓志高,等.那林金矿全面留矿法试验研究[J].黄金科学技术,2008,16(6):36- 40.
[2]广西壮族自治区第二地质一队.广西凌云县明山矿区金矿普查报告[R].广西:广西壮族自治区第二地质一队,1993.
[3]姚香,郭树林,王劼,等.分段崩落采矿法在岩金矿山的试验与应用[C] // 全国采矿论坛峰会论文集. 南宁,2008,85- 90.
[4] 采矿手册编委会.采矿手册(第二卷)[M]. 北京:冶金工业出版社,1991.
[5]长春黄金研究院.凤山县宏益矿业有限责任公司无底柱分段崩落采矿法试验研究总结报告[R].长春:长春黄金研究院,2009.
[6]中国国家标准化管理委员会.中华人民共和国国家标准,金属非金属矿山安全规程(GB16423- 2006)[M]. 北京:中国标准出版社,2006:34- 36.
[7]罗铁牛.独立采空区稳定性研究与经验教训[J]. 黄金科学技术,2003,11(2):33- 37.
[8]郑永学.矿山岩体力学[M].北京:冶金工业出版社,1988:211- 215.
[9]周科平.采矿环境再造技术与复杂难采矿体开采[J].全国采矿论坛峰会论文集,2008:65- 75.

[1] DING Jianfeng,LIU Fengtao,CHEN Guoping,WANG Fang,CHEN Bingyu,WU Zhiming,WANG Li,. Study and Application of Chemical Grouting in Sanshandao Gold Mine [J]. J4, 2012, 20(4): 54-57.
[2] XUE Tianxi,LIU Xuesheng,LI Heping,GONG Xinyuan. The Practice and Application of Control Certex by Association to Metamorphic Gold Deposit in Hexi [J]. J4, 2004, 12(5): 44-48.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!