Question exists which in view of the Hulalin minning area even tunnels construction,proposed set of pratical and feasible means.
Key words: even tunnels construction, vertical cutting, artillery hole, arrangement, weight of chage, cost
CLC Number:
SUN Hu,SONG Guibin. Tunnels Job of Halalin Minning Area Practice Analysis[J].J4, 2007, 15(6): 38-42.