Approach Some Technology Problems Encountering in the Design and Operation of Shaft's Sump

HE Jianhua   

  1. Hetai Gold Mine,Guangdong Gaoyao 526127,China
  • Received:2003-10-23 Revised:2003-12-04 Online:2004-02-28 Published:2011-09-15

Abstract:

The shaft's sump can be used as reserve water、form a sediment and clear up.According to mine's different characters of water-bearing、pouring out water volume,as well as normal displacement and drainage time to decide the sump's volume.In order to reduce mining engineering amount,we should abide by connected operation regulations,on the basis of mine's extraction and whether need to drain mud.

Key words: Sump, Designed regulation, Account of pouring out water volume, Operation technology

CLC Number: 

  • TD853.11

[1]  采矿设计手册编委会.采矿设计手册(井巷工程卷)[M].北京:中国建筑工业出版社,1989.
[2]  采矿设计手册编委会.采矿设计手册(矿产地质卷下)[M].北京:中国建筑工业出版社,1989.
[3]  矿山地质手册编委会.矿山地质手册[M].北京:冶金工业出版社,1995.

[1] GAO Guang. A Feasibility Study on Selection of Conceal Silo Location [J]. J4, 2006, 14(5): 34-37.
[2] GUO Qiangjun. The Directional Measure of the Blind Silo [J]. J4, 2004, 12(3): 46-48.