Gold Science and Technology ›› 2021, Vol. 29 ›› Issue (3): 401-410.doi: 10.11872/j.issn.1005-2518.2021.03.174

• Mining Technology and Mine Management • Previous Articles    

Experimental Study on Precise Delay Hole-by-Hole Blasting Vibration Reduction of Underground Blasting

Xianglong LI1,2(),Qihu ZHANG1(),Jianguo WANG1,Deyuan YANG3,Bin LI4,Xingbiao ZHU4   

  1. 1.Faculty of Land Resources Engineer,Kunming University of Science and Technology,Kunming 650093,Yunnan,China
    2.Key Laboratory of Development and Utilization of Zhongde Blue Mine and Special Underground Mine,Kunming 650093,Yunnan,China
    3.Dahongshan Iron Mine,Kunming Iron & Steel Group Co. ,Ltd. ,Xinping 653100,Yunnan,China
    4.Yongshan Jinsha Mine Co. ,Ltd. ,Yongshan 657305,Yunnan,China
  • Received:2020-09-27 Revised:2021-02-09 Online:2021-06-30 Published:2021-07-14
  • Contact: Qihu ZHANG E-mail:lxl00014002@163.com;zhang18487084511@163.com

Abstract:

The interference vibration reduction technology based on precise delay hole by hole initiation is not only an effective means to reduce blasting vibration,but also can improve the effect of rock fragmentation and realize the active control of blasting vibration effect and harm.The key of this technology is to calculate the accurate and reasonable delay time under the conditions of reasonable hole layout parameters,single hole charge and charge structure conditions.However,due to the low time delay accuracy and instability of the conventional ordinary nonel detonator,the effect of controlling the millisecond delay interval to reduce the blasting vibration is not good.Engineering blasting operations are mostly carried out in complex environments and have strict requirements on blasting vibration.Combining previous research results,an accurate and reasonable delay time for underground shallow hole blasting was given.At the same time,combined with the field test research,the application of accurate delay time in reducing blasting vibration was explored.In view of the fact that the digital electronic detonator initiation network can realize the precise control of the delay time of precise delay hole by hole initiation,the delay time can be set flexibly and the performance is stable,using high-precision and high-strength digital electronic detonator,the field test of precise delay hole by hole initiation was designed and carried out.And the vibration waveform velocity of vibration time history signal was analyzed by using MA-TLAB 18.0. In the field test,vector synthesis of the waveform can be obtained,and the peak velocity of the vibration waveform under the delay time between holes of 25 ms is reduced by 27%,8%,29%,52% compared with the peak velocity of 15,20,30,35 ms successively.The peak value of the vibration waveform velocity under the delay time between rows of 75 ms is reduced by 28%,26% and 23% compared with the delay of 25 ms,125 ms and 200 ms between rows of single row blastholes.The test results show that the reasonable delay time between holes and rows can effectively reduce the blasting vibration intensity.

Key words: precision delay, hole-by-hole initiation, peak vibration velocity, vibration intensity, waveform fusion, interference vibration reduction, field test

CLC Number: 

  • TD235

Fig.1

Schematic diagram of detonation network for the first test"

Fig.2

Blasting vibration waveform of the first test"

Fig.3

Synthesis diagram of blasting vibration vector of the first test"

Fig.4

Schematic diagram of detonation network for the second test"

Fig.5

Blasting vibration waveform of the second test"

Fig.6

Synthesis diagram of blasting vibration vector of the second test"

Fig.7

Schematic diagram of detonation network for the third test"

Fig.8

Blasting vibration waveform of the third test"

Fig.9

Synthesis diagram of blasting vibration vector of the third test"

Fig.10

Effect diagram of blasting"

Blair D P,2009.Limitations of electronic delays for the control of blast vibration and fragmentation[C]//Proceedings of the 9th International Symposium on Rock Fragmentation by Blasting.Granada:The Chemical Rubber Company Press:171-184.
Chen Shihai,Yan Yongfeng,Qi Guifeng,al et,2011.Analysis of influencing factors on seismic reduction effect of millisecond blasting[J].Geotechnical Mechanics,32(10):3003-3008.
Chen Shouru,Li Yanling,Xie Shengquan,2004.Experimental study on blasting technology with step interference in open pit stope[J].Journal of Hunan University of Science and Technology (Natural Science Edition),19(2):10-13.
Cheng Ming,2020. Research on Blasting Parameters and Hole-by-hole Initiation Optimization of 108 and 402 Sections of Jinsha Mining[D].Kunming:Kunming University of Science and Technology.
Fang Guifu,Fang Chun,Liu Xiankui,al et,2011.Delay optimization engineering practice of electronic detonator for urban blasting[J].Engineering Blasting,17(3):81-84.
Gao Wenxue,Liu Hongyu,Liu Hongyang,al et,2010.Analysis of the influence of blasting excavation on the stability of high cutting slope[J].Journal of Rock Mechanics and Engineering,29 (Supp.1):2982-2987.
Gao Wenxue,Liu Yuntong,2003.Energy dissipation of rock damage under impact load[J].Journal of Rock Mechanics and Engineering,22(11):1777-1780.
Gong Min,Shi Facai,Wu Xiaodong,2019.Study on delay time of electronic detonator based on superposition and spectrum analysis[J].Journal of Vibration and Shock,38(15):134-141.
Guo Xuebin,Xiao Zhengxue,Zhang Zhicheng,2001.Slope effect of blasting vibration[J].Journal of Rock Mechanics and Engineering,20(1):83-87.
Han Liang,Li Hongjiang,Liu Dianshu,al et,2019.Probability analysis of detonator delay error on superposition and vibration reduction of seismic waves[J].Journal of Vibration and Shock,38(3):96-101,124.
Hu Guiying,Liu Kewei,Du Xin,al et,2018.Research on smooth cut blasting technology and its application in roadway excavation[J].Gold Science and Technology,26(3):349-356.
Li Shunbo,Yang Jun,2013.Numerical simulation of the influence of different millisecond delay between holes on blasting vibration[J].Journal of Coal Society,38(Supp.2):325-330.
Liao Zhiqin,Wang Liguan,He Zhengxiang,2020.Feature extraction and classification of mine microseismic signals based on EEMD and correlation dimension[J].Gold Science and Technology,28 (4):585-594.
Ling Tonghua,Li Xibing,2004.Identification of actual delay time in millisecond blasting by wavelet transform[J].Journal of Hunan University of Science and Technology (Natural Science Edition),19(2):21-23.
Ling Tonghua,Zhang Sheng,Yi Zhiqiang,al et,2012.EMD analysis of energy distribution characteristics of rock acou-stic emission signal[J].Journal of Vibration and Shock,31(11):26-31.
Liu Yuntong,Gao Wenxue,2001.Numerical simulation of rock damage under blast load[J].Journal of Rock Mechanics and Engineering,20(6):789-792.
Qiu X,Shi X,Gou Y,al et,2018.Short-delay blasting with single free surface:Results of experimental tests [J].Tunnelling &Underground Space Technology,74:119-130.
Qiu Xianyang,Shi Xiuzhi,Zhou Jian,al et,2017.Vibration reduction effect analysis of high precision detonator short millisecond blasting based on HHT energy spectrum[J].Explosion and Shock Waves,37(1):107-113.
Richards A B,Moore A J,2017.Factors affecting frequency control of blast vibration[C]//New Development on Engineering Blasting.Beijing:Metallurgical Industry Press:305-310.
Song Guangming,Zeng Xinwu,Chen Shouru,al et,2003.Vibration reduction time selection based on wavelet packet analysis model of waveform prediction[J].Explosion and Shock Waves,23(2):163-168.
Xing Guangwu,Zhang Beilong,Ji Zhenxi,2016.Directional blasting demolition of 120 m chimney in Wushadesheng power plant,Shunde[J].Blasting,33(3):92-95.
Xu Zhenyang,Yang Jun,Chen Zhanyang,al et,2014.Study on energy distribution of blasting seismic wave[J].Journal of Vibration and Shock,33(11):38-42.
Yang Guoliang,Jiang Linlin,Yang Renshu,2013.Study on double wedge deep hole cutting blasting[J].Journal of China University of Mining and Technology,42(5):755-760.
Yang J H,Lu W B,Jiang Q H,al et,2016.Frequency comparison of blast-induced vibration per delay for the full-face millisecond delay blasting in underground opening excavation[J].Tunnelling & Underground Space Technology Incorporating Trenchless Technology Research,51:189-201.
Yang Nianhua,Zhang Le,2012.Numerical prediction method of blasting vibration wave superposition[J].Explosion and Shock Waves,32(1):84-90.
Yang Renshu,Fu Xiaoqiang,Yang Guoliang,al et,2017.Application of EMD and FSWT combination method in blasting vibration signal analysis[J].Journal of Vibration and Shock,36(2):58-64.
Zhang Guangxiong,Yang Jun,Lu Hongwei,2009.Study on vibration reduction effect of millisecond delay blasting[J].Engineering Blasting,15(3):17-21.
Zhang Liang,Ling Tonghua,Chen Zenghui,al et,2020.Determination of actual delay time of millisecond blasting based on improved CEEMDAN method[J].Explosion and Shock Waves,39(20):274-280.
Zhang Yiping,Li Xibing,Zhao Guoyan,al et,2005.Time frequency analysis of blasting vibration signal[J].Journal of Geotechnical Engineering,27(12):1472-1477.
Zhang Zhicheng,2013.Control of engineering blasting[J].Journal of Underground Space and Engineering,9(5):1208-1214.
Zhao Mingsheng,Liang Kaishui,Yu Deyun,al et,2012.Analysis of influence of segment number on time frequency characteristics of blasting vibration signal[J].Journal of Coal Society,37(1):55-61.
Zheng Guichu,Xing Guangwu,2019.Demolition of 120 m reinforced concrete chimney by controlled blasting[J].Mining Technology,19(4):128-131.
Zhong Dongwang,He Li,Cao Peng,al et,2016.Analysis of blasting vibration duration and optimization of delay time of millisecond blasting[J].Explosion and Shock Waves,36(5):703-709.
陈士海,燕永峰,戚桂峰,等,2011.微差爆破降震效果影响因素分析[J].岩土力学,32(10):3003-3008.
陈寿如,李雁翎,谢圣权,2004.露天采场台阶干扰降震爆破技术试验研究[J].湖南科技大学学报(自然科学版),19(2):10-13.
程明,2020.金沙矿业108、402矿段爆破参数及逐孔起爆优化研究[D].昆明:昆明理工大学.
方桂富,方春,刘先魁,等,2011.城镇爆破电子雷管延时优选工程实践[J].工程爆破,17(3):81-84.
高文学,刘宏宇,刘洪洋,等,2010.爆破开挖对路堑高边坡稳定性影响分析[J].岩石力学与工程学报,29(增1):2982-2987.
高文学,刘运通,2003.冲击载荷作用下岩石损伤的能量耗散[J].岩石力学与工程学报,22(11):1777-1780.
龚敏,石发才,吴晓东,2019.基于叠加和频谱分析的电子雷管延期时间研究[J].振动与冲击,38(15):134-141.
郭学彬,肖正学,张志呈,2001.爆破振动作用的坡面效应[J].岩石力学与工程学报,20(1):83-87.
韩亮,李红江,刘殿书,等,2019.雷管延期误差对地震波叠加降振的概率分析[J].振动与冲击,38(3):96-101,124.
胡桂英,刘科伟,杜鑫,等,2018.光面掏槽爆破技术的研究及其在巷道掘进中的应用[J].黄金科学技术,26(3):349-356.
李顺波,杨军,2013.孔间不同毫秒延时对爆破振动影响的数值模拟[J].煤炭学报,38(增2):325-330.
廖智勤,王李管,何正祥,2020.基于EEMD和关联维数的矿山微震信号特征提取和分类[J].黄金科学技术,28(4):585-594.
凌同华,李夕兵,2004.用小波变换识别微差爆破中的实际延迟时间[J].湖南科技大学学报(自然科学版),19(2):21-23.
凌同华,张胜,易志强,等,2012.岩石声发射信号能量分布特征的EMD分析[J].振动与冲击,31(11):26-31.
刘运通,高文学,2001.爆炸荷载下岩石损伤的数值模拟研究[J].岩石力学与工程学报,20(6):789-792.
邱贤阳,史秀志,周健,等,2017.基于HHT能量谱的高精度雷管短微差爆破降振效果分析[J].爆炸与冲击,37(1):107-113.
宋光明,曾新吾,陈寿如,等,2003.基于波形预测小波包分析模型的降振微差时间选择[J].爆炸与冲击,23(2):163-168.
邢光武,张北龙,姬震西,2016.顺德五沙德胜电厂120 m烟囱定向爆破拆除[J].爆破,33(3):92-95.
徐振洋,杨军,陈占扬,等,2014.爆破地震波能量分布研究[J].振动与冲击,33(11):38-42.
杨国梁,姜琳琳,杨仁树,2013.复式楔形深孔掏槽爆破研究[J].中国矿业大学学报,42(5):755-760.
杨年华,张乐,2012.爆破振动波叠加数值预测方法[J].爆炸与冲击,32(1):84-90.
杨仁树,付晓强,杨国梁,等,2017.EMD和FSWT组合方法在爆破振动信号分析中的应用研究[J].振动与冲击,36(2):58-64.
张光雄,杨军,卢红卫,2009.毫秒延时爆破干扰降振作用研究[J].工程爆破,15(3):17-21.
张亮,凌同华,陈增辉,等,2020.基于改进CEEMDAN方法确定微差爆破实际延期时间[J].振动与冲击,39(20):274-280.
张义平,李夕兵,赵国彦,等,2005.爆破震动信号的时频分析[J].岩土工程学报,27(12):1472-1477.
张志呈,2013.工程爆破的控制[J].地下空间与工程学报,9(5):1208-1214.
赵明生,梁开水,余德运,等,2012.段数对爆破振动信号的时频特性影响分析[J].煤炭学报,37(1):55-61.
郑桂初,邢光武,2019.120 m钢筋混凝土烟囱控制爆破拆除[J].采矿技术,19(4):128-131.
钟冬望,何理,操鹏,等,2016.爆破振动持时分析及微差爆破延期时间优选[J].爆炸与冲击,36(5):703-709.
[1] Peng JIN,Kewei LIU,Xudong LI,Jiacai YANG. Numerical Simulation Study of Crack Propagation in Deep Rock Mass Under Water-coupling Blasting [J]. Gold Science and Technology, 2021, 29(1): 108-119.
[2] Honglu FEI,Yu LIU,Qifei QIAN,Qiang SU,Xiaoyu SUN. Distribution of Blasthole Fracture in Eccentric Charge Under In-situ Stress [J]. Gold Science and Technology, 2020, 28(2): 228-237.
[3] Chaoqun HAN,Jianhong CHEN,Zhiyong ZHOU,Shan YANG. Research on Prediction of Rock Mass Blastability Classification Based on PCA-SVM Model [J]. Gold Science and Technology, 2019, 27(6): 879-887.
[4] Qiyue LI,Xinhao ZHAO,Xin’ao WEI,Jing ZHENG,Jianqiu ZHANG. Study and Application of Contour Control Blasting Technology for Large Section Tunnel [J]. Gold Science and Technology, 2019, 27(3): 350-357.
[5] WANG Haibo, WEI Guoli, ZONG Qi, XU Ying. Numerical Simulation and Application Research on Joint Development Rock Roadway Blasting Excavation [J]. Gold Science and Technology, 2018, 26(3): 342-348.
[6] LIU Liansheng,LIU Jiangchao,DONG Guifa,LIAO Minmin,CAI Jiande. [J]. Gold Science and Technology, 2016, 24(5): 73-79.
[7] GUO Jiang,CUI Wenqiang,CHEN Hui. Numerical Analysis of the Smooth Blasting Crack Development under Different Coupling Medium [J]. Gold Science and Technology, 2016, 24(1): 68-75.
[8] LI Xibing,ZHU Wei,LIU Weijun,ZHANG Deming. Research on Rock Mass Blastability Based on Principal Component Analysis and RBF Neural Network [J]. Gold Science and Technology, 2015, 23(6): 58-63.
[9] YANG Yong,QIU Yingkui,YANG Jie,HE Guoqiang,LIU Junxiao. Study on Optimization of Blasting Technology in Jiaojia Gold Mine,Shandong Province [J]. Gold Science and Technology, 2012, 20(6): 79-81.
[10] YU Changxian,ZHAO Mingxuan,LI Xiaodong. Application of Long-hole Shock Controlled Blasting in Sanshandao Gold Mine [J]. J4, 2012, 20(4): 58-61.