Application of Multi-period Variable Frequency Air Distribution Method in Ventilation System of Meishan Iron Mine

  • Zhicheng XU ,
  • Weiwei JU
Expand
  • 1.Nanjing Baodi Meishan Production City Development Co. ,Ltd. ,Mining Branch,Nanjing 210012,Jiangsu,China
    2.Sinosteel Ma’anshan Institute of Mining Research Co. ,Ltd. ,Ma’anshan 243000,Anhui,China
    3.State Key Laboratory of Safety and Health for Metal Mine,Ma’anshan 243000,Anhui,China
    4.Huawei National Engineering Research Center Co. ,Ltd. ,of High Efficiency Cyclic Utilization of Metal Mineral Resources,Ma’anshan 243000,Anhui,China

Received date: 2020-03-17

  Revised date: 2020-09-21

  Online published: 2021-03-22

Abstract

Meishan iron mine adopts the ventilation system of four-stage progressive return fan station,with many main fans and wide distribution.In order to strengthen the management of ventilation system,the remote control system of multi-stage fan station of the mine was gradually established in 2006.Main fans are equipped with frequency converter,total installed capacity of 15 main fans is 2 730 kW,actual power consumption of full-time operation is 1 940.76 kW,and the annual ventilation cost is up to 14.4509 million Yuan.If the ventilation of working faces with constant air volume according to the maximum demand,it shall be inevitably result in the waste of air volume and energy consumption.At present,changing the characteristic curves of the main fans to adjust the air volume can be achieved by adjusting the installation angle of the blade or the frequency conversion of 1 Hz amplitude,but this method is time-consuming,laborious and difficult,and the method of precise frequency modulation to adjust the air volume is relatively weak.Therefore,based on the theory of “balance of supply and demand”,ventilation period is divided into three,according to the number of mining face,driving working face,other working faces and chambers,and given a certain air leakage coefficient to determine the actual air volume in three periods for ventilation on demand,which can maximize the effect of ventilation and energy saving.According to the relationship between frequency,rotation speed and air volume in the theory of electromotor and fluid mechanics,the actual operating frequency of each main fan meeting the mine air demand in three periods was calculated accurately.Each main fan is precisely and remotely frequency modulated by PLC remote control system,which simplifies the complicated regulation mode of ventilation management personnel adjusting air volume by frequency 1 Hz.After normal operation,the actual air volume in three periods can meet the requirements,and the actual power consumption in each period is 1 093.28 kW,1 385.06 kW and 1 786.38 kW.Through the implementation of research plan of multi time precise frequency conversion and energy saving ventilation technology,the ventilation cost of mine ventilation system is saved by 3.865 million Yuan per year,which solves the problems of air volume,energy consumption and waste caused by full ventilation of the mine ventilation system.The effect is remarkable,which embodies the advanced nature of modern mine ventilation and energy saving technology,and fully displays the advantages of multi-stage time station frequency conversion ventilation “intelligent” energy saving.

Cite this article

Zhicheng XU , Weiwei JU . Application of Multi-period Variable Frequency Air Distribution Method in Ventilation System of Meishan Iron Mine[J]. Gold Science and Technology, 2021 , 29(1) : 129 -135 . DOI: 10.11872/j.issn.1005-2518.2021.01.059

References

null Chatterjee A,Zhang L J,Xia X H,2015.Optimization of mine ventilation fan speeds according to ventilation on demand and time of use tariff [J].Applied Energy,146:65-73.
null Cui Renjie,2017.Application of frequency converter in energy saving monitoring system of coal mine ventilator[J].Coal and Chemical Industry,(12):86-93.
null Ge Qifa,Yu Runcang,Zhu Weigen,al et,2017a.Application of VOD ventilation new technology in a mine project [J].China Nonferrous Metallurgy,(6):58-63.
null Ge Qifa,Zhu Weigen,Zhu Ruijun,al et,2017b.Research of mining method and ventilation control for difficult-to-mine ore bodies in deep mine[J].Nonferrous Metals Engineering,7(6):86-89,99.
null Gong Suoguo,Hong Houshan,Huang Xin,al et,2002.Computerized centralized monitoring system for the ventilation of multistage fan stations[J].Metal Mine,(4):49-52.
null Guo Yi,Wu Suzhen,Wenjuan Lü,2007.The energy-saving analysis of the frequency converter in the course of the fan moving[J].Journal of Zhengzhou Econom ICS & Management Institute,(9):90-92.
null Han Jing,Ding Changdong,Jiang Shuguang,al et,2016.Mathematical model of reliability evaluation on air volume of ventilation system in volume adjustment by frequency conversion[J].Journal of Safety Science and Technology,(3):143-148.
null Hu Y N,Koroleva O I,Krstic M,2003.Nonlinear control of mine ventilation networks[J].Systems & Control Letters, 49(4):239-254.
null Jia Anmin,2012.Remote monitoring and energy saving research of multistage fan station ventilation[J].Metal Mine,(6):113-119.
null Ju Hesen,Huang Shouyuan,2013.Optimization and reformation of ventilation system in Datuanshan mining area of Dongguashan copper mine[J].Modern Mining,(7):98-100.
null Li G,Kocsis C,Hardcastle S,2011.Sensitivity analysis on parameter changes in underground mine ventilation systems[J].Journal of Coal Science & Engineering,17(3) :251-255.
null Liu Jie,Xie Xianping,2010.Principle of energy saving of multi-fan and multistage fan station ventilation system[J].Metal Mine,(5) :71-74.
null Liu Jiefeng,2013.Energy-saving analysis of frequency conversion technology in ventilation system[J].Jiangxi Coal Science & Technology,(2):134-135.
null Nie Wenyan,Jin Lin,Wang Zhonggen,2006.Application of variable frequency technology and fuzzy control for local ventilators.[J].Coal Mine Machinery,(8):147-149.
null Pan Junyi,Zhang Tao,Cai Shunshuo,al et,2002.Construction and experience of ventilation system in the second stage of Meishan iron mine[J].Metal Mine,(11):53-55.
null Sun Lin,Guo Liang,2005.Shaft ventilating system based on technique of speed control by frequency variation[J].Mining Engineering,(6):55-56.
null Wang Jianbo,Zhou Wei,Wu Lengjun,al et,2015.Application of centralized remote control technology in the balance regulation of the ventilation system air pressure[J].Metal Mine,(4):282-286.
null Wang Tiantao,2010.Frequency conversion technology and its application in mine main fan[J].Coal,19(3):43-45.
null Wang Xiaodong,2018.Analysis of intelligent ventilation system in modern mines[J].Energy and Energy Conservation,(10):175-176.
null Wu Hailiang,Wang Peng,Pan Junyi,al et,2014.Study on underground VOD intelligent ventilation technology of metal mine[J].Metal Mine,(6):123-127.
null Xu Ruilong,Shi Shengrong,1985.The optimal method of air distribution needed—The method of path[J].Journal of Fuxin Mining Institute, 4(2):61-69.
null Yang Jie,Zhao Liangang,Quan Fang,2015.Current situation of coal mine ventilation system and design of intelligent ventilation system[J].Industry and Mine Automation,41(11):74-77.
null Yuan Meifang,2013.Control of the underground main fan speed and air output with LOGO time-sharing and frequency conversion[J].Metal Mine,(8):138-140.
null Zhang Sasa,Ren Gaofeng,Zhang Congrui,al et,2015.Intellisense and remote centralized security monitoring system for the ventilation system in deep mining[J].Journal of Wuhan University of Technology,37(1):104-108.
null 崔仁杰,2017.变频器在煤矿通风机节能监控系统中应用研究[J].煤炭与化工,(12):86-93.
null 葛启发,于润沧,朱维根,等,2017a.按需通风技术在某矿山工程设计中的应用[J].中国有色冶金,(6):58-63.
null 葛启发,朱维根,朱瑞军,等,2017b.深井难采矿体开采与通风控制技术研究[J].有色金属工程,7(6):86-89,99.
null 贡锁国,洪候山,黄欣,等,2002.多级机站通风计算机集中监控系统[J].金属矿山,(4):49-52.
null 郭怡,吴素珍,吕文娟,2007.变频器在风机运行中的节能分析[J].郑州经济管理干部学院学报,(9):90-92.
null 韩靖,丁长栋,蒋曙光,等,2016.变频调风时通风系统风量可靠性评价数学模型[J].中国安全生产科学技术,(3):143-148.
null 贾安民,2012.井下多级机站通风监控与节能技术研究[J].金属矿山,(6):113-119.
null 琚和森,黄寿元,2013.冬瓜山铜矿大团山采区通风系统优化改造[J].现代矿业,(7):98-100.
null 刘杰,谢贤平,2010.多风机多级机站通风节能原理初探[J].金属矿山,(5):71-74.
null 刘杰峰,2013.变频技术在矿井通风系统中的节能分析[J].江西煤炭科技,(2):134-135.
null 聂文艳,金林,王仲根,2006.变频技术和模糊控制在局部通风机中的应用[J].煤矿机械,(8):147-149.
null 潘军义,张涛,蔡顺朔,等,2002.梅山铁矿二期通风系统的建设和经验[J].金属矿山,(11):53-55.
null 孙林,郭亮,2005.基于变频调速技术的计算机矿井压风系统[J].矿业工程,(6):55-56.
null 王剑波,周伟,吴冷峻,等,2015.远程集中控制技术在调节通风系统风压平衡中的应用[J].金属矿山,(4):282-286.
null 王天涛,2010.变频技术及其在矿井主扇中的应用[J].煤,19(3):43-45.
null 王晓东,2018.现代矿井智能通风系统分析[J].能源与节能,(10):175-176.
null 伍海亮,王鹏,潘军义,等,2014.金属矿山井下VOD 智能通风技术研究[J].金属矿山,(6):123-127.
null 徐瑞龙,施圣荣,1985.矿井按需分风的优化方法——通路法[J].阜新矿业学院学报,4(2):61-69.
null 杨杰,赵连刚,全芳,2015.煤矿通风系统现状及智能通风系统设计[J].工矿自动化,41(11):74-77.
null 袁梅芳,2013.LOGO分时段变频控制井下主风机转速及输出风量[J].金属矿山,(8):138-140.
null 张卅卅,任高峰,张聪瑞,等,2015.深部开采矿井通风智能感知及风机远程集中安全监控系统[J].武汉理工大学学报,37(1):104-108.
Outlines

/