Process Design Optimization and Application of a Dressing and Metallurgy Pilot Plant in Qinghai
Received date: 2019-06-20
Revised date: 2019-09-29
Online published: 2020-02-26
青海某金矿新建30 t/d选冶中试厂,选冶工艺以浮选和环保提金剂浸出工艺为主,主要针对金矿资源选冶新工艺、新技术、新药剂、新材料和自动化控制等在工业生产应用前的中试验证及优化试验进行系统研究。中试厂原设计流程单一,无法满足工艺流程优化试验研究的需求,通过对该中试厂工艺流程设计进行优化,实现了不同试验工艺流程的组合和调整,在小试研究结果基础上对该矿山2个矿区的矿石分别进行工艺优化中试研究,研究成果成功应用于选厂实际生产中,黄龙沟矿区矿石回收率由77.51%提高至82.48%,年新增产值883.45万元。
李飞 , 陈自强 . 青海某金矿选冶中试厂工艺设计优化及应用[J]. 黄金科学技术, 2020 , 28(1) : 142 -147 . DOI: 10.11872/j.issn.1005-2518.2020.01.080
A 30 t/d dressing and metallurgy pilot plant have been completed for a gold mine in Qinghai Province.The processing technologies of the pilot plant are flotation and gold leaching by environmental extraction agent.The pilot plant is mainly aimed at the pilot test study for gold ore dressing and metallurgy of new techniques,new materials and new technologies,new reagents and automatic control,etc. At the same time,it can carry out the flotation technology research for nonferrous metals.Mainly equipment in the pilot plant was monitored by frequency conversion,so that it can study the technical measures to improve equipment operation rate.The original design flow of the pilot plant is single,so it cannot carry out process optimization experiment research.Base on optimizing the process designs,different process test can be combination and adjustment.Through the open-circuit tests of laboratory for Huanglonggou gold ore and Shuizhadonggou gold ore in this mine,the recovery rate of the rougher flotation,the once scavenging,the second scavenging,the third scavenging for Shuizhadonggou gold ore is 80.41%,6.55%,1.47%,0.67%,and the grade of secondary cleaning concentrate is 30.40×10-6,so the suitable flotation process for Shuizhadonggou gold ore is single stage rough two stage cleaning three stage scavenging;the recovery rate of the rough flotation,the once scavenging,the second scavenging,the third scavenging for Huanglonggou gold ore is 75.95%,3.53%,2.32%,1.52%,and the grade of rough flotation concentrate is 29.51×10-6,so the suitable flotation process for Huanglonggou gold ore is single stage rough three stage scavenging.Based on the results of laboratory tests for these two minerals,the pilot tests were carried out in the pilot plant,which was aimed at demonstrating the results of the laboratory tests.Finally,this research result was successfully applied to the actual production of plants,the flotation process of the second plant was optimized to a single stage roughing three stage scavenging.As a result,the recovery rate of Huanglonggou gold ore is increased to 82.48% from 77.51%,more than 66.88 kg gold is additionally recovered per year,and the annual increase in production value reaches 8 834 500 yuan.
| 1 |
王晓芒,朱龙根,王卫荣.加速中试基地建设促进科技成果转化[J].研究与发展管理,1995(5):21-24.
|
| 2 |
奚正平.破解中试难题[J].中国人才,2013(3):39.
|
| 3 |
邵丽莉,徐晓波.中试基地的建设[J].浙江化工,2001,32(3):10-12.
|
| 4 |
鲍林,黄朗喜.科技成果转化的中试环节建设[J].研究与发展管理,2002,14(4):30-34.
|
| 5 |
陈建中,胡家乐.科技成果转化难问题探析[J].安徽科技,2005(4):38-39.
|
| 6 |
张晋虎,王成一,赵景荣.关于中试基地建设中的几个问题[J].研究与发展管理,1993(3):58-59.
|
| 7 |
符建峰.产业化论证:科技成果转化的必要环节[J].中国高校科技,2014(11):90-91.
|
| 8 |
高玉祥,葛藟.试论科研单位中试基地的建设[J].农机化研究,1993(1):54-56.
|
| 9 |
杨世中,宋春雷,胡江南.选矿自动化在高原矿山的应用[J].有色金属(选矿部分),2013(2):59-63.
|
| 10 |
明平田,毕文.选矿自动化在金辉矿业的应用[J].武汉工程大学学报,2011,33(2):92-95.
|
| 11 |
明平田,夏明强,王万芳.提高青海某金矿浮选回收率试验[J].现代矿业,2012(4):62-64.
|
| 12 |
许庆砚,李程伟,苏惠民.印尼某难选冶金矿石选矿试验研究[J].黄金,2015,36(4):59-62.
|
| 13 |
姚鲁之.论“多碎少磨”的工艺与装备[J].新世纪水泥导报,2001(6):29-30.
|
| 14 |
冯国俊.多碎少磨 增产降耗[J].有色金属(选矿部分),1996(4):22-26.
|
| 15 |
方文,尚海洋,站立岗,等.破碎控制系统在选矿生产过程的应用[J].中国科技纵横,2014(19):55-56.
|
| 16 |
冯立琴,徐应军.磨矿分级过程的自动控制[J].甘肃冶金,2012(6):123-126.
|
| 17 |
陶建利,周清波.贵州某金矿选矿试验研究[J].矿冶工程,2013,33(1):52-55.
|
| 18 |
陈贵烽,李文郁,王昱.浮选过程工艺参数的自动化控制[J].选煤技术,1993(6):23-26.
|
| 19 |
刘世理,訾涛,朱再胜,等.选煤厂浮选工艺实现自动化控制的探讨[J].山西焦煤科技,2011,35(1):50-52.
|
| 20 |
李剑铭,刘万峰,马子龙,等.某金矿矿石浮选优化试验研究[J].有色金属(选矿部分),2004(3):16-18.
|
| 21 |
王楠,杨守斌,蔡有国,等.某金矿浮选流程优化试验研究[J].黄金,2015,36(8):44-48.
|
/
| 〈 |
|
〉 |